Fire Protection Flagged at Inspection? What to Do Before Handover in Singapore

You have just finished a renovation, A&A works or a change of use, and the fire safety inspection flags the structural steel: fire protection missing, damaged or not to the required rating. Handover is delayed until it is put right. This is one of the most common reasons we get called in, and in most cases it can be fixed quickly once the cause is clear.

Why fire protection on steel gets flagged

From site experience, these are the usual reasons:

  • Coating removed during works – vermiculite or board encasement hacked off to fix brackets, run M&E services or install new partitions, then never reinstated.
  • Damaged coating – cracked, hollow or flaking vermiculite from impact, vibration or water leakage.
  • New steel left bare – new beams, mezzanines, staircases or platforms added without fire protection.
  • Wrong system or thickness – a decorative paint used instead of a fire-rated coating, or the coating applied too thin for the rating required.
  • No records – the work may be fine, but there are no product details, thickness readings or photos to show it.

What to do next

1. Get the exact comment in writing. Ask your Qualified Person (QP) or consultant which members are affected and what fire resistance period is required (for example 1 hour or 2 hours). This decides the system and thickness.

2. Identify the existing system. Is it spray vermiculite, intumescent paint or board encasement? Repairs should match the original system where possible, or use a system the consultant accepts.

3. Repair or apply to the required rating. Damaged vermiculite is cut back to sound material and reinstated. Bare steel gets a fire protection system sized for the steel section and rating. Intumescent paint is applied in coats until the specified dry film thickness is reached.

4. Keep the evidence. Photos before, during and after, the product data and thickness readings. This is what your QP needs to close the matter.

Vermiculite or intumescent paint for the fix?

For hidden steel above ceilings, in plant rooms or warehouses, spray vermiculite is usually the practical and economical choice. For exposed steel where appearance matters – staircases, canopies, shopfront steelwork – intumescent paint gives a smooth painted finish. For a short comparison, see our guide to intumescent paint for steel staircases and repairing damaged vermiculite on metal columns.

Avoid these mistakes

  • Patching vermiculite with ordinary cement or plaster – it does not provide the fire rating.
  • Painting over damaged fire protection to hide it.
  • Applying intumescent paint over rust or an incompatible primer – it may not perform or may peel.
  • Waiting until the week of handover. Some systems need curing time between coats.